Lake Michigan College Campus Transformation Timeline
Construction began on June 4, 2018.
Work Completed
Wave 1 – June 2018 to Sept. 2018
- Large Lecture Hall Renovations
- New HVAC for D-wing
- New Arts & Science Faculty Offices
- Central Duplication Relocation
Wave 2 – Sept. 2018 to Jan. 2019
- Relocated IT Offices
- New HVAC for B-wing
- General Classroom Upgrades
- New Start-to-Finish Offices
- New Student Support Service Lab & Offices
- New EOC Offices
- New Health Sciences Simulation Labs
- New Nursing Education Center
- Central Duplication Relocation
Wave 3 – Jan. 2019 to May 2019
- New Health Science Department Offices
- Finalize Renovation of the Health Sciences Center
- Advising Suite Renovation
- New Veterans' Lounge
Wave 4 – Mar. 2019 to June 2019
- New Welcome Center
- Admissions/Records/Financial Aid Office Renovation
- New EOC Offices
- General Classroom Upgrades
Wave 5 – May 2019 to December 2019
- New Learning Resource Center (LRC)
- New Teaching Learning Center (TLC)
- New Tutoring & Testing Center
- New Writing/ESL Center
- Renovated Culinary Program Kitchen & Teaching Space
- New College Multipurpose Room
- Relocated Art Classrooms
- New HVAC for L-wing
- Mendel Center Jenkins Theatre Rigging & Fire Suppression Upgrades - Complete Sept 2019
- Mendel Center Grand Upton Hall Remodel – Complete Sept 2019
Wave 6 – Nov. 2019 to March 2020
- Renovated General Classrooms
- New HVAC for A-wing
- Mendel Center Hanson Theatre Remodel - Complete Jan 2020
- Mendel Center Energy Upgrades - Complete Feb 2020
- Fitness Center in D-Wing - Complete Feb 2020
Construction complete in 2020.